The use of distributed power generation has advantage as well as disadvantage. One of the disadvantages is that the plant requires a dependable redundancy system to provide back up of power during failure of its power generation equipment. This paper presents a study on techno-economic assessment of redundancy systems for a cogeneration plant. Three redundancy systems were investigated; using public utility,generator set and gas turbine as back up during failures. Results from the analysis indicate
that using public utility provides technical as well as economic advantages in comparison
to using generator set or turbine as back up. However, the economic advantage of the
public utility depends on the frequency of failures the plant will experience as well on the
maximum demand charge. From the break even analysis of the understudied plant, if the
number of failures exceeds 3 failures per year for the case of maximum demand charge of
RM56.80, it is more economical to install a generator set as redundancy. The study will be
useful for the co-generator operators to evaluate the feasibility of redundancy systems.

Item Type: Citation Index Journal
Departments / MOR / COE: Departments > Mechanical Engineering
Depositing User: AP Ir Dr Mohd Amin Abd Majid
Date Deposited: 28 Apr 2015 02:54
Last Modified: 28 Apr 2015 02:54
URI: http://scholars.utp.edu.my/id/eprint/11640

Actions (login required)

View Item
View Item