Matrix Integration of Schedule & Cost to Predict Offshore Structure Project Cost

Ty, Phuor and Sambu Potty, Narayanan and Akram, M. K. M (2014) Matrix Integration of Schedule & Cost to Predict Offshore Structure Project Cost. In: 2014 IEEE Colloquium on Humanities, Science and Engineering (CHUSER 2014), 7 - 8 April, 2014, Penang Malaysia.

[thumbnail of conference] PDF (conference)
Final revised paper for Chuser2014revised2.pdf
Restricted to Registered users only

Download (410kB) | Request a copy

Abstract

This paper discusses an interrelationship between
the cost and schedule by using the cost/schedule data sets of the
actual offshore construction project. It presents the method to
define the offshore work packages from the complex work and
cost breakdown structures that is a very vital key to have success
in forecasting the total project cost. The predicted total project
cost is simulated considering the time value of money and the
allocated resource factor that strongly depend on the interest rate
and the allocated time for each resource, respectively. The
calculations are based on mathematical matrix manipulations.
The model is developed based on an actual case study on the
offshore construction project. The budgeted cost of work
scheduled (BCWS), budgeted cost of work performed (BCWP),
actual cost of work performed (ACWP), cost performance index
(CPI), and schedule performance index (SPI) are computed
based on the matrices.

Item Type: Conference or Workshop Item (Paper)
Uncontrolled Keywords: Integrating Schedule and Cost; Matrix; Resource Allocation; Time Value; Overhead Cost.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Departments / MOR / COE: Research Institutes > Institute for Sustainable Building
Depositing User: DR NARAYANAN SAMBU POTTY
Date Deposited: 21 Apr 2014 04:55
Last Modified: 19 Jan 2017 08:20
URI: http://scholars.utp.edu.my/id/eprint/11223

Actions (login required)

View Item
View Item